SupportP1





Project Start:
Project Finish:
Thu 4/1/99
Thu 6/10/99


Tasks


IDTask NameDurationStartFinishResource Names% Complete
1Planning19 daysThu 4/1/99Thu 4/22/99 0%
2Review IS421 Analysis6 daysThu 4/1/99Thu 4/8/99All0%
3Create Project Plan8 daysFri 4/9/99Sat 4/17/99All0%
4Conduct of Project (Deliv. A)8 daysThu 4/1/99Sun 4/11/99All0%
5Meeting with Instructor (Tent. -Before Class 5:15)1 dayThu 4/22/99Thu 4/22/99All0%
6      
7Repository37 daysFri 4/23/99Tue 6/8/99 0%
8Open Web site Account 1 dayFri 4/23/99Fri 4/23/99Zeeshan0%
9Initial Version Implemented9 daysFri 4/23/99Tue 5/4/99Zeeshan0%
10Update Version as new information is created28 daysWed 5/5/99Tue 6/8/99Zeeshan0%
11      
12Design30 daysSun 4/18/99Sun 5/23/99Juan0%
13Team Meeting ( 5:15pm - 8th Floor, DePaul Center)1 dayThu 4/29/99Thu 4/29/99All0%
14Meeting with Instructor(Tent. -5:15pm - Danny's Office)1 dayThu 5/6/99Thu 5/6/99All0%
15Team Meeting (9:00am - 11th Floor, DePaul Center)1 daySat 5/8/99Sat 5/8/99All0%
16User-Interface Design 23 daysTue 4/27/99Sun 5/23/99Juan0%
17Initial Design5 daysTue 4/27/99Sat 5/1/99Juan0%
18Detailed Design6 daysMon 5/3/99Sat 5/8/99Juan0%
19Final Design12 daysSun 5/9/99Sun 5/23/99Juan0%
20      
21Database Design12 daysSun 4/18/99Sat 5/1/99Julio0%
22Normalize ER Diagram11 daysSun 4/18/99Fri 4/30/99Julio0%
23Database Schema6 daysMon 4/26/99Sat 5/1/99Julio0%
24Data Definition Language6 daysMon 4/26/99Sat 5/1/99Julio0%
25Create Database in Access4 daysWed 4/28/99Sat 5/1/99Julio0%
26      
27End-User Help Design 23 daysTue 4/27/99Sun 5/23/99Adam0%
28Initial Design5 daysTue 4/27/99Sat 5/1/99Adam0%
29Detailed Design6 daysMon 5/3/99Sat 5/8/99Adam0%
30Final Design12 daysSun 5/9/99Sun 5/23/99Adam0%
31      
32Report Design23 daysTue 4/27/99Sun 5/23/99Zeeshan0%
33Initial Design5 daysTue 4/27/99Sat 5/1/99Zeeshan0%
34Detailed Design6 daysMon 5/3/99Sat 5/8/99Zeeshan0%
35Final Design12 daysSun 5/9/99Sun 5/23/99Zeeshan0%
36      
37Prototype Design8 daysThu 5/13/99Sun 5/23/99All0%
38Process Design23 daysTue 4/27/99Sun 5/23/99Sophia0%
39Initial Design5 daysTue 4/27/99Sat 5/1/99Sophia0%
40Detailed Design6 daysMon 5/3/99Sat 5/8/99Sophia0%
41Final Design12 daysSun 5/9/99Sun 5/23/99Sophia0%
42      
43      
44      
45Prototype Coding22 daysThu 5/13/99Thu 6/10/99 0%
46User-Interface22 daysThu 5/13/99Thu 6/10/99Juan0%
47Database22 daysThu 5/13/99Thu 6/10/99Julio0%
48Report22 daysThu 5/13/99Thu 6/10/99Zeeshan0%
49Programs22 daysThu 5/13/99Thu 6/10/99Sophia0%
50End-User Help22 daysThu 5/13/99Thu 6/10/99Adam0%
51Meeting with Instructor(Tent -5:15pm - Danny's Office)1 dayThu 5/20/99Thu 5/20/99All0%
52      
53      
54Testing16 daysFri 5/21/99Thu 6/10/99All0%

Resources


IDNameGroupMax UnitsPeak Units
1Adam 100%300%
2All 100%200%
3Julio 100%500%
4Juan 100%400%
5Zeeshan 100%400%
6Sophia 100%300%

Assignments


Task IDTask NameResource NameWorkStartFinish% Work Complete
2Review IS421 AnalysisAll48 hrsThu 4/1/99Thu 4/8/990%
3Create Project PlanAll64 hrsFri 4/9/99Sat 4/17/990%
4Conduct of Project (Deliv. A)All64 hrsThu 4/1/99Sun 4/11/990%
5Meeting with Instructor (Tent. -Before Class 5:15)All8 hrsThu 4/22/99Thu 4/22/990%
12DesignJuan240 hrsSun 4/18/99Sun 5/23/990%
16User-Interface Design Juan184 hrsTue 4/27/99Sun 5/23/990%
21Database DesignJulio96 hrsSun 4/18/99Sat 5/1/990%
27End-User Help Design Adam184 hrsTue 4/27/99Sun 5/23/990%
32Report DesignZeeshan184 hrsTue 4/27/99Sun 5/23/990%
37Prototype DesignAll64 hrsThu 5/13/99Sun 5/23/990%
38Process DesignSophia184 hrsTue 4/27/99Sun 5/23/990%
13Team Meeting ( 5:15pm - 8th Floor, DePaul Center)All8 hrsThu 4/29/99Thu 4/29/990%
14Meeting with Instructor(Tent. -5:15pm - Danny's Office)All8 hrsThu 5/6/99Thu 5/6/990%
54TestingAll128 hrsFri 5/21/99Thu 6/10/990%
46User-InterfaceJuan176 hrsThu 5/13/99Thu 6/10/990%
47DatabaseJulio176 hrsThu 5/13/99Thu 6/10/990%
48ReportZeeshan176 hrsThu 5/13/99Thu 6/10/990%
49ProgramsSophia176 hrsThu 5/13/99Thu 6/10/990%
50End-User HelpAdam176 hrsThu 5/13/99Thu 6/10/990%
51Meeting with Instructor(Tent -5:15pm - Danny's Office)All8 hrsThu 5/20/99Thu 5/20/990%
8Open Web site Account Zeeshan8 hrsFri 4/23/99Fri 4/23/990%
9Initial Version ImplementedZeeshan72 hrsFri 4/23/99Tue 5/4/990%
10Update Version as new information is createdZeeshan224 hrsWed 5/5/99Tue 6/8/990%
24Data Definition LanguageJulio48 hrsMon 4/26/99Sat 5/1/990%
23Database SchemaJulio48 hrsMon 4/26/99Sat 5/1/990%
22Normalize ER DiagramJulio88 hrsSun 4/18/99Fri 4/30/990%
25Create Database in AccessJulio32 hrsWed 4/28/99Sat 5/1/990%
15Team Meeting (9:00am - 11th Floor, DePaul Center)All8 hrsSat 5/8/99Sat 5/8/990%
41Final DesignSophia96 hrsSun 5/9/99Sun 5/23/990%
40Detailed DesignSophia48 hrsMon 5/3/99Sat 5/8/990%
39Initial DesignSophia40 hrsTue 4/27/99Sat 5/1/990%
35Final DesignZeeshan96 hrsSun 5/9/99Sun 5/23/990%
19Final DesignJuan96 hrsSun 5/9/99Sun 5/23/990%
18Detailed DesignJuan48 hrsMon 5/3/99Sat 5/8/990%
17Initial DesignJuan40 hrsTue 4/27/99Sat 5/1/990%
34Detailed DesignZeeshan48 hrsMon 5/3/99Sat 5/8/990%
33Initial DesignZeeshan40 hrsTue 4/27/99Sat 5/1/990%
30Final DesignAdam96 hrsSun 5/9/99Sun 5/23/990%
29Detailed DesignAdam48 hrsMon 5/3/99Sat 5/8/990%
28Initial DesignAdam40 hrsTue 4/27/99Sat 5/1/990%