| ID | Task Name | Duration | Start | Finish | Resource Names | % Complete |
| 1 | Planning | 19 days | Thu 4/1/99 | Thu 4/22/99 | | 0% |
| 2 | Review IS421 Analysis | 6 days | Thu 4/1/99 | Thu 4/8/99 | All | 0% |
| 3 | Create Project Plan | 8 days | Fri 4/9/99 | Sat 4/17/99 | All | 0% |
| 4 | Conduct of Project (Deliv. A) | 8 days | Thu 4/1/99 | Sun 4/11/99 | All | 0% |
| 5 | Meeting with Instructor (Tent. -Before Class 5:15) | 1 day | Thu 4/22/99 | Thu 4/22/99 | All | 0% |
| 6 | | | | | | |
| 7 | Repository | 37 days | Fri 4/23/99 | Tue 6/8/99 | | 0% |
| 8 | Open Web site Account | 1 day | Fri 4/23/99 | Fri 4/23/99 | Zeeshan | 0% |
| 9 | Initial Version Implemented | 9 days | Fri 4/23/99 | Tue 5/4/99 | Zeeshan | 0% |
| 10 | Update Version as new information is created | 28 days | Wed 5/5/99 | Tue 6/8/99 | Zeeshan | 0% |
| 11 | | | | | | |
| 12 | Design | 30 days | Sun 4/18/99 | Sun 5/23/99 | Juan | 0% |
| 13 | Team Meeting ( 5:15pm - 8th Floor, DePaul Center) | 1 day | Thu 4/29/99 | Thu 4/29/99 | All | 0% |
| 14 | Meeting with Instructor(Tent. -5:15pm - Danny's Office) | 1 day | Thu 5/6/99 | Thu 5/6/99 | All | 0% |
| 15 | Team Meeting (9:00am - 11th Floor, DePaul Center) | 1 day | Sat 5/8/99 | Sat 5/8/99 | All | 0% |
| 16 | User-Interface Design | 23 days | Tue 4/27/99 | Sun 5/23/99 | Juan | 0% |
| 17 | Initial Design | 5 days | Tue 4/27/99 | Sat 5/1/99 | Juan | 0% |
| 18 | Detailed Design | 6 days | Mon 5/3/99 | Sat 5/8/99 | Juan | 0% |
| 19 | Final Design | 12 days | Sun 5/9/99 | Sun 5/23/99 | Juan | 0% |
| 20 | | | | | | |
| 21 | Database Design | 12 days | Sun 4/18/99 | Sat 5/1/99 | Julio | 0% |
| 22 | Normalize ER Diagram | 11 days | Sun 4/18/99 | Fri 4/30/99 | Julio | 0% |
| 23 | Database Schema | 6 days | Mon 4/26/99 | Sat 5/1/99 | Julio | 0% |
| 24 | Data Definition Language | 6 days | Mon 4/26/99 | Sat 5/1/99 | Julio | 0% |
| 25 | Create Database in Access | 4 days | Wed 4/28/99 | Sat 5/1/99 | Julio | 0% |
| 26 | | | | | | |
| 27 | End-User Help Design | 23 days | Tue 4/27/99 | Sun 5/23/99 | Adam | 0% |
| 28 | Initial Design | 5 days | Tue 4/27/99 | Sat 5/1/99 | Adam | 0% |
| 29 | Detailed Design | 6 days | Mon 5/3/99 | Sat 5/8/99 | Adam | 0% |
| 30 | Final Design | 12 days | Sun 5/9/99 | Sun 5/23/99 | Adam | 0% |
| 31 | | | | | | |
| 32 | Report Design | 23 days | Tue 4/27/99 | Sun 5/23/99 | Zeeshan | 0% |
| 33 | Initial Design | 5 days | Tue 4/27/99 | Sat 5/1/99 | Zeeshan | 0% |
| 34 | Detailed Design | 6 days | Mon 5/3/99 | Sat 5/8/99 | Zeeshan | 0% |
| 35 | Final Design | 12 days | Sun 5/9/99 | Sun 5/23/99 | Zeeshan | 0% |
| 36 | | | | | | |
| 37 | Prototype Design | 8 days | Thu 5/13/99 | Sun 5/23/99 | All | 0% |
| 38 | Process Design | 23 days | Tue 4/27/99 | Sun 5/23/99 | Sophia | 0% |
| 39 | Initial Design | 5 days | Tue 4/27/99 | Sat 5/1/99 | Sophia | 0% |
| 40 | Detailed Design | 6 days | Mon 5/3/99 | Sat 5/8/99 | Sophia | 0% |
| 41 | Final Design | 12 days | Sun 5/9/99 | Sun 5/23/99 | Sophia | 0% |
| 42 | | | | | | |
| 43 | | | | | | |
| 44 | | | | | | |
| 45 | Prototype Coding | 22 days | Thu 5/13/99 | Thu 6/10/99 | | 0% |
| 46 | User-Interface | 22 days | Thu 5/13/99 | Thu 6/10/99 | Juan | 0% |
| 47 | Database | 22 days | Thu 5/13/99 | Thu 6/10/99 | Julio | 0% |
| 48 | Report | 22 days | Thu 5/13/99 | Thu 6/10/99 | Zeeshan | 0% |
| 49 | Programs | 22 days | Thu 5/13/99 | Thu 6/10/99 | Sophia | 0% |
| 50 | End-User Help | 22 days | Thu 5/13/99 | Thu 6/10/99 | Adam | 0% |
| 51 | Meeting with Instructor(Tent -5:15pm - Danny's Office) | 1 day | Thu 5/20/99 | Thu 5/20/99 | All | 0% |
| 52 | | | | | | |
| 53 | | | | | | |
| 54 | Testing | 16 days | Fri 5/21/99 | Thu 6/10/99 | All | 0% |